FLHigh Solar Potential

Renewable Energy Permitting in Florida

The Sunshine State offers excellent solar irradiance and growing utility-scale development, though permitting varies by county.

Get Florida Permitting Intelligence

Florida Energy Market Overview

Installed Capacity
20.2 GW

Key Permitting Highlights in Florida

Solar property tax exemption

Net metering available

Growing utility-scale investment

Hurricane-resilient system requirements

Overview

Florida's permitting landscape includes both local and state pathways depending on project size. Large thermal plants and certain facilities trigger the Power Plant Siting Act (PPSA), while most solar and BESS projects proceed through local zoning plus standard environmental permits and utility interconnection.

Permitting Guide

Siting Decision

Large power facilities can run through the Florida Power Plant Siting Act (state certification).

Core Permits

FDEP ERP (wetlands/stormwater), NPDES CGP, coastal consistency/management, species, local comp plan/zoning (unless preempted by certification path).

Common Challenges & Landmines

Wetlands + flood + coastal constraints; hurricanes drive design standards and local resistance. Local moratoria + ordinance churn (solar setbacks, BESS bans, decommissioning bonds) are usually the #1 surprise cost. Stormwater + erosion compliance (CGP/SWPPP) enforcement risk + stop-work exposure. Wetlands/401/404 + floodplain can be route/site killers—plan alternatives early.

Tax Considerations

Expect county property tax to dominate economics. Property tax is commonly local and negotiable; incentives are often deal-specific.

Data Center Considerations

Water + wastewater + storm hardening + back-up generation permitting; site selection is the permit strategy. Florida has a defined data center property sales tax exemption framework with specific eligibility criteria and certification mechanics.

Power Plant Siting Act (PPSA)

The PPSA provides a centralized state process for large facilities where a single certification replaces local and state permits. The Florida DEP coordinates the process with the Governor and Cabinet issuing final certification. Many utility-scale solar projects are configured below 75 MW specifically to avoid triggering PPSA certification requirements.

Local & Environmental Permitting

For most solar/BESS projects, local entitlements are often the hardest part due to Florida's extensive wetlands, drainage requirements, and community optics. Expect substantial engineering and mitigation planning for wetlands, streams, and stormwater. Screen environmental constraints early—they can significantly reshape project design.

Utility Interconnection

Florida is not an ISO/RTO-driven market like ERCOT or CAISO. Interconnection is utility-administered through the major IOUs (FPL, Duke Energy Florida, Tampa Electric). Process timelines and costs vary by utility territory.

Frequently Asked Questions

What triggers the Power Plant Siting Act?

The PPSA applies to large thermal plants and certain configurations. Many developers configure solar projects below 75 MW to avoid PPSA certification. Below that threshold, projects go through local zoning plus standard environmental permits.

What are the main permitting challenges in Florida?

Wetlands, drainage, and stormwater requirements are typically the most complex permitting issues. Florida's extensive wetland coverage means most sites require careful environmental screening and often significant mitigation planning.

How Spark Accelerates Development in Florida

Our AI-powered platform provides instant access to zoning ordinances, permit requirements, and community sentiment data specific to Florida jurisdictions.

Zoning Analysis

Instantly access Florida zoning codes and land use regulations for any parcel.

Permit Tracking

Monitor permit timelines and requirements across Florida jurisdictions.

Community Sentiment

Understand local attitudes toward energy development in Florida communities.

Ready to develop in Florida?

Get instant access to permitting intelligence for Florida and accelerate your projects.