Data Center Rankings by State

A state-by-state ranking of U.S. data center buildout activity, built from Spark's proprietary infrastructure database of permitting and construction milestones.

Ranked by the Spark Data Center Score — a weighted blend of total data centers filed, in construction, or operating, permit-filing momentum, permit approval rate, and active moratoria — alongside the underlying figures for every state.

5,000+

Data centers filed, in construction, or operating

81.9%

National approval rate, 2024–2026

+26%

Average permit-filing growth rate (Q1 - Q2 2026)

Texas

#1 ranked state

Executive summary

The state of data center buildout activity, drawn straight from the ranking below.

Texas remains the clear leader with a Spark Data Center Score of 71, just ahead of #2 Virginia; all other states rank significantly lower.

Since Jan 1, 2026, the top 5 has shifted: Pennsylvania climbed into the top 5, rising from #8 to #4, while Georgia dropped out, falling from #5 to #17, driven by a steep rise in moratoria and a drop-off in new permits filed.

National approval rate for data center permits sits at 81.9%, with permit filings up an average of +26% across states between the first halves of 2025 and 2026.

Iowa has the largest share of counties with an active data center moratorium, at 10.1%.

All 50 states, ranked

Hover or tap a state on the map for its ranking, or sort the table by any column. Click “Guide” on any row for Spark's full permitting and zoning guide for that state.

Color map by:
Spark Data Center Score:LowHighNo data

Click any column header to sort.

Rankvs Jan 1StateSpark ScoreData CentersY/Y GrowthApproval RateMoratoria
1
TexasTX
Guide
71814+16.2%81.7%0.4%
2
VirginiaVA
Guide
58660-19.1%77%1.1%
3▲ 1
OhioOH
Guide
37241+37.8%87.5%1.1%
4▲ 4
PennsylvaniaPA
Guide
35228+48.9%67.7%0%
5▼ 2
CaliforniaCA
Guide
33252-33.3%88.2%1.7%
6▲ 3
WashingtonWA
Guide
3185+25%100%0%
7▲ 5
AlabamaAL
Guide
3150+100%87.5%0%
8▼ 2
ArizonaAZ
Guide
311450%84%0%
9▲ 19
WyomingWY
Guide
3060+84.6%83.7%0%
10▲ 10
North CarolinaNC
Guide
30120+40.7%78.1%0%
11▲ 3
MississippiMS
Guide
2956+87.5%94.3%1.2%
12▲ 9
MontanaMT
Guide
2944+77.8%88.9%0%
13▲ 10
MissouriMO
Guide
2990+66.7%83.8%0.9%
14▲ 10
MarylandMD
Guide
2987-4.3%94.3%0%
15▼ 8
New JerseyNJ
Guide
2983-9.1%95.8%0%
16▼ 6
OregonOR
Guide
2894-25%92.5%0%
17▼ 12
GeorgiaGA
Guide
28283-12.5%84.5%5.6%
18▲ 7
South CarolinaSC
Guide
2775+75%92.3%2.2%
19▲ 27
New HampshireNH
Guide
275+100%0%
20▲ 18
Rhode IslandRI
Guide
275+100%0%
21▲ 8
AlaskaAK
Guide
2714+33.3%100%0%
22▲ 21
ConnecticutCT
Guide
2717+100%77.8%0%
23▲ 11
LouisianaLA
Guide
2769+16.7%85.9%0%
24▼ 2
New MexicoNM
Guide
2651+83.3%70.8%0%
25▼ 14
OklahomaOK
Guide
2656+33.3%81.2%0%
26▼ 11
HawaiiHI
Guide
26120%100%0%
27▼ 11
West VirginiaWV
Guide
2633-17.2%97%0%
28▲ 16
ColoradoCO
Guide
2563+50%81.8%1.6%
29▼ 12
New YorkNY
Guide
25206-19%72.7%3.2%
30
ArkansasAR
Guide
2431+14.3%92.9%1.3%
31▲ 4
MinnesotaMN
Guide
2373+28.6%73.9%1.1%
32▲ 18
MaineME
Guide
2320+100%57.1%0%
33▲ 8
KentuckyKY
Guide
2343-18.2%83.3%0%
34▼ 21
IllinoisIL
Guide
23193-18.5%84.4%4.9%
35▼ 17
WisconsinWI
Guide
2290+26.7%80.7%2.8%
36▲ 3
VermontVT
Guide
2220%0%
37▼ 11
NebraskaNE
Guide
2153+33.3%100%4.3%
38▼ 7
MichiganMI
Guide
21102+65.2%65.8%3.6%
39▼ 7
IdahoID
Guide
2123+20%66.7%0%
40▲ 2
FloridaFL
Guide
2070+72.7%78.3%4.5%
41▼ 5
IndianaIN
Guide
20152+1.8%82.4%5.4%
42▼ 9
MassachusettsMA
Guide
2018-66.7%84.6%0%
43▼ 6
NevadaNV
Guide
18130+22.2%81.7%6.2%
44▼ 25
UtahUT
Guide
1884+55.6%91.5%6.9%
45▼ 5
South DakotaSD
Guide
1813-33.3%100%3%
46▼ 1
TennesseeTN
Guide
1879-44.8%93.5%4.2%
47▲ 2
North DakotaND
Guide
1573-20%88.2%5.7%
48
KansasKS
Guide
1232-14.3%86.2%5.7%
49▼ 2
IowaIA
Guide
1187+33.3%93.5%10.1%
50▼ 23
DelawareDE
Guide
49-20%0%0%

Methodology

  • Data centers (filed, in construction, or operating) — distinct data center projects in Spark's infrastructure database that have reached at least one of these stages on or before 2026-07-11: a permit filed, construction started, or fully operational. This is a pipeline count, not just currently-live facilities, and it counts individually tracked projects rather than individual buildings — a single large campus can span many buildings under one or a handful of tracked projects.
  • Permits filed (Jan to Jun 2025 / 2026) — count of permit-filed milestones logged for data center projects in the same six-month window (January 1 – June 30) of each year, so the two years compare like for like.
  • Growth rate — the change in permit filings between the two half-year windows, calculated as (2026 filings − 2025 filings) ÷ (2026 filings + 2025 filings). This symmetric formula is bounded to ±100%, so a state going from a near-zero base doesn't produce a runaway percentage.
  • Approval rate (2024–2026) — of the permit decisions (approved or denied) recorded for data center projects between January 2024 and 2026-07-11, the share that were approved. Permits still pending a decision are excluded. States with a “—” had no decided permits in this window.
  • Active moratoria — the share of a state's counties with a currently active, adopted data-center moratorium, out of all counties in the state (townships and other sub-county jurisdictions aren't counted). If a state has adopted a genuine statewide moratorium, this shows 100% regardless of county count. Determined from a text-based classification of authority decisions, so treat it as directional rather than a legal determination.
  • Spark Data Center Score — a proprietary 0–100 composite. Total data centers, permit-filing growth rate, approval rate, and active-moratoria share are each min-max normalized against a shared reference range spanning both the current and Jan 1, 2026 snapshots (rather than each snapshot's own independent range), then combined as 50% total data centers (filed, in construction, or operating), 20% approval rate, 10% permit-filing growth rate, and −20% active moratoria (a higher share of active moratoria pulls the score down). Using a shared range keeps the two snapshots on the same scale, so a state's score only moves when its own underlying numbers change — not simply because another state pulled further ahead. States with no decided permits are assigned the median approval rate across states that have one in that snapshot, so a thin sample doesn't unfairly tank the score. Rank reflects this score, highest to lowest.
  • vs Jan 1 — how a state's rank has moved since Jan 1, 2026.
  • Data is sourced from Spark's proprietary infrastructure tracking database, covering permitting authority decisions, hearings, and construction/operational milestones nationwide. Figures reflect what has been captured and verified as of the data cutoff and will shift as new filings and decisions are recorded.

Planning a data center in one of these states?

Get a permit matrix with a jurisdiction-level breakdown of zoning, permitting, and approval timelines for your specific site.

Explore permit matrices