US data center map & rankings, tracked by state
Tracking one of the largest infrastructure efforts in US history, with state-by-state data on where the buildout stands today — and where moratoria and permitting momentum are making it harder to build next.
Spark's unique county- and state-level dataset tracks more than 20,000 infrastructure projects, including the data centers already approved, under construction, and in operation across the US. We've built our nationwide dataset bottom-up from local permitting and construction records tracked across all 3,000+ US counties, giving the most complete picture available of data center locations and us data centers by state.
33%
Share of the national data center pipeline in Texas, Virginia, and Georgia
Filed, in construction, or operating · filings +59% year-over-year
72%
National approval rate, Q3 2026
-5 pts vs 77% in H1 2026
+23%
National permit-filing growth rate (Q3 2025 vs Q3 2026)
Q3 2026 filings vs. Q3 2025, all states
Texas
#1 ranked state
Holding the top spot since 2024
Executive summary
Where are data centers located across the US? The ranking below draws straight from Spark's live buildout data, state by state.
Texas has been the #1 ranked state since 2024, with a Spark Data Center Score of 94, up 3 points since the H1 ranking. The 2nd-highest ranked state, Virginia, has risen 3 points over the same time period.
Since the end of H1, the top 5 has shifted: Louisiana climbed from #21 to #5 on a 100% approval rate in the period, while Mississippi dropped out, falling from #5 to #26.
The national approval rate for data center permits fell to 72% in Q3, down from 77% in H1 and 83% a year earlier. That's the lowest rate for US permit approvals since we started tracking in 2021.
Public opposition kept spreading in Q3: 11.7% of data center projects drew opposition, up from a 9.5% quarterly average in H1. Moratoria grew faster, with localities enacting them up 71% over the H1 quarterly pace, and negative sentiment now covers 78% of classified county readings.
The data center map: all 50 states, ranked
Hover or tap a state on the data center map for its ranking, or sort the table by any column. This data center locations map covers all 50 states.

Did data centers swing the midterms? Not the way you think.
Voters in the top data center states swung toward Democrats, but candidates' positions on data centers didn't move votes. Our analysis of the 2026 midterms.
Read the analysisReport: Pushback goes statewide in Q3 2026
In Q3, data center resistance kept growing and moved, in many cases, to the state level. Every measure of resistance ran ahead of its H1 pace, the national approval rate fell for the second straight quarter, and New York, Texas, and Pennsylvania each acted to slow, audit, or condition new projects. Changes below are measured since the end of H1 2026.
The national approval rate for data center permits fell to 72% in Q3 2026
Approval rates are shares of decided permits; small samples can swing sharply.
States stepped in
Four policy moves in Q3 put a large share of proposed data center capacity under new conditions. New York's order is the most direct, pausing nearly every large project in the state's pipeline. Capacity figures are Spark estimates of proposed, pre-construction capacity.
| Initiative | Date | Projects covered | Est. proposed capacity exposed | Nature of risk |
|---|---|---|---|---|
| New York statewide pause | Jul 14 | Data centers of 50 MW or more | 25–50 GW | Environmental permits paused for up to a year |
| Texas ERCOT audit and Batch Zero pause | Aug 3 | Large loads in ERCOT's interconnection process | 100–340 GW (75 MW+) | Grid studies delayed; noncompliant projects may be denied grid access |
| Pennsylvania executive order | Aug 18 | Data centers over 25 MW applying after Aug 18 | 60–145 GW | New cost, water, and community conditions; slower review without the state agreement |
| Federal Ratepayer Protection Act | Passed House; stalled in Senate | All new large loads, via state rules | 0.8–1.8 TW nationwide | Indirect: encourages states to make developers cover grid costs |
New York
Gov. Hochul's executive order pauses environmental permits for data centers of 50 MW or more for up to a year while the state develops a generic environmental impact statement covering energy, water, and air. The legislature's broader bill, at a 20 MW threshold with new electric and water rate classes, awaits her signature, and she will also seek to repeal data center sales tax exemptions. Most proposed New York projects sit above the 50 MW line, so a 20 MW threshold would add little capacity.
Texas
On Aug 3, Gov. Abbott directed the PUCT and ERCOT to audit data center projects in the interconnection process. ERCOT paused Batch Zero, its first large-load study group of about 300 data centers of 75 MW or more. Local approvals rose to 89% in Q3, yet the bottleneck has moved from the county board to the grid. Watch the Dec 10 audit filing; the original April 2027 study date is expected to slip.
Pennsylvania
Gov. Shapiro's order makes data centers responsible for grid upgrade costs, requires them to bring or buy their own capacity, file water plans, and offer community benefit agreements. Projects over 25 MW that sign the state's template agreement get rolling review; others face sequential review, and all data centers leave the state's permit fast-track program. The approval rate rose from 61% to 72%, consistent with clearer rules rather than a freeze.
Federal and other states
The House passed the Ratepayer Protection Act 417–3; it encourages, but does not require, states to make developers cover grid and generation costs. It stalled in the Senate, where a Sept 30 vote to begin debate fell short, 57–43. Michigan bills would pause key data center approvals until Apr 1, 2027, and Utah's governor set a higher bar on water, air, and local impacts.
Click any column header to sort.
| Rank▲ | vs H1 | State | Spark ScoreSpark's proprietary 0–100 composite score, weighing total data centers, approval rate, permit-filing growth rate, active moratoria share, and opposition events per project (moratoria and opposition both pull the score down). | Pipeline IndexEach state's data center pipeline (projects with a permit filed, construction started, or fully operational), indexed so the largest state = 100. A relative measure: it shows how states compare, not absolute project counts. | Y/Y GrowthChange in permit filings between Q3 2025 and Q3 2026: (2026 filings − 2025 filings) ÷ (2026 filings + 2025 filings). Bounded to ±100%, so a near-zero base doesn't produce a runaway percentage. | Approval RateShare of decided data center permits (approved or denied) in Q3 2026 that were approved - the same 3-month window used for the growth-rate column, so the two line up. Pending permits are excluded. | MoratoriaShare of a state's counties with a currently active data-center moratorium, out of all counties in the state (townships and other sub-county jurisdictions are rolled up to their county). A state with a genuine statewide moratorium shows 100%. | OppositionHow much public pushback data center projects face in the state, per project, in Q3 2026 - contested hearings, organized resident opposition, flagged social posts, etc. A higher figure pulls the Spark Score down. |
|---|---|---|---|---|---|---|---|---|
| 1 | — | TexasTX | 94 | 100 | +43% | 89% | 2% | 0.08 |
| 2 | — | VirginiaVA | 85 | 76 | +9% | 57% | 4.6% | 0.12 |
| 3 | ▲ 1 | CaliforniaCA | 74 | 32 | 0% | 95% | 12% | 0.13 |
| 4 | ▲ 6 | PennsylvaniaPA | 74 | 32 | +49% | 72% | 4.5% | 0.26 |
| 5 | ▲ 16 | LouisianaLA | 72 | 9 | +20% | 100% | 3.1% | 0.23 |
| 6 | ▲ 22 | IllinoisIL | 71 | 20 | +39% | 88% | 11.8% | 0.15 |
| 7 | ▼ 1 | OregonOR | 70 | 12 | +39% | 60% | 2.8% | 0.11 |
| 8 | ▲ 11 | West VirginiaWV | 70 | 4 | +33% | 100% | 0% | 0.40 |
| 9 | ▼ 6 | ArizonaAZ | 70 | 17 | -33% | 71% | 0% | 0.10 |
| 10 | ▲ 1 | GeorgiaGA | 69 | 33 | +21% | 71% | 16.1% | 0.19 |
| 11 | ▲ 7 | New JerseyNJ | 69 | 11 | +6% | 88% | 4.8% | 0.21 |
| 12 | ▲ 1 | HawaiiHI | 69 | 1 | 0% | — | 0% | 0.00 |
| 13 | ▲ 3 | Rhode IslandRI | 68 | 1 | 0% | — | 0% | 0.00 |
| 14 | ▲ 19 | MissouriMO | 68 | 10 | +33% | 85% | 5.3% | 0.33 |
| 15 | ▼ 6 | AlabamaAL | 68 | 6 | +63% | 91% | 1.5% | 0.59 |
| 16 | ▲ 27 | MinnesotaMN | 68 | 9 | +56% | 88% | 8% | 0.25 |
| 17 | — | VermontVT | 68 | 0 | 0% | — | 0% | 0.00 |
| 18 | ▲ 8 | North DakotaND | 68 | 9 | +54% | 100% | 13.2% | 0.05 |
| 19 | ▲ 4 | NebraskaNE | 67 | 7 | +25% | 100% | 10.8% | 0.10 |
| 20 | ▲ 15 | South DakotaSD | 67 | 2 | +100% | 75% | 6.1% | 0.00 |
| 21 | ▲ 6 | OklahomaOK | 67 | 9 | +67% | 50% | 1.3% | 0.20 |
| 22 | ▼ 2 | WyomingWY | 67 | 7 | +50% | 80% | 4.3% | 0.42 |
| 23 | ▼ 9 | WashingtonWA | 67 | 11 | +46% | 100% | 12.9% | 0.12 |
| 24 | ▲ 8 | TennesseeTN | 67 | 10 | +47% | 100% | 12.6% | 0.35 |
| 25 | ▲ 17 | UtahUT | 67 | 11 | +50% | 100% | 17.2% | 0.24 |
| 26 | ▼ 21 | MississippiMS | 66 | 7 | -60% | 65% | 1.2% | 0.11 |
| 27 | ▼ 3 | NevadaNV | 65 | 14 | +60% | 83% | 18.4% | 0.17 |
| 28 | ▼ 20 | ArkansasAR | 65 | 5 | -56% | 25% | 2.7% | 0.05 |
| 29 | ▲ 1 | ColoradoCO | 65 | 9 | +38% | 88% | 15.6% | 0.21 |
| 30 | ▲ 1 | North CarolinaNC | 64 | 15 | +21% | 65% | 12% | 0.15 |
| 31 | ▼ 9 | New HampshireNH | 64 | 1 | +100% | — | 0% | 1.22 |
| 32 | ▼ 7 | MontanaMT | 64 | 4 | -60% | 0% | 1.8% | 0.45 |
| 33 | ▼ 21 | KentuckyKY | 63 | 6 | +67% | 70% | 5.8% | 0.62 |
| 34 | ▼ 27 | AlaskaAK | 63 | 2 | +60% | 100% | 5.9% | 0.63 |
| 35 | ▲ 1 | IndianaIN | 63 | 16 | -20% | 86% | 21.7% | 0.17 |
| 36 | ▲ 4 | KansasKS | 62 | 5 | +100% | 79% | 12.4% | 0.63 |
| 37 | ▼ 22 | ConnecticutCT | 59 | 2 | -33% | — | 17.7% | 0.31 |
| 38 | ▼ 4 | IdahoID | 59 | 4 | +14% | 0% | 4.5% | 0.18 |
| 39 | ▼ 2 | South CarolinaSC | 58 | 9 | 0% | 65% | 21.7% | 0.12 |
| 40 | ▲ 7 | MaineME | 57 | 2 | +100% | 100% | 25% | 0.42 |
| 41 | — | IowaIA | 57 | 10 | 0% | 50% | 26.2% | 0.25 |
| 42 | ▼ 13 | OhioOH | 57 | 26 | 0% | 44% | 26.1% | 0.25 |
| 43 | ▲ 1 | FloridaFL | 55 | 8 | +20% | 39% | 17.9% | 0.25 |
| 44 | ▼ 5 | New MexicoNM | 54 | 6 | +27% | 24% | 3% | 0.80 |
| 45 | — | MichiganMI | 53 | 12 | -14% | 58% | 27.7% | 0.43 |
| 46 | ▲ 2 | MassachusettsMA | 53 | 2 | 0% | 0% | 28.6% | 0.46 |
| 47 | ▼ 9 | DelawareDE | 50 | 1 | -100% | 0% | 33.3% | 0.18 |
| 48 | ▼ 2 | WisconsinWI | 48 | 10 | +2% | 24% | 26.4% | 0.29 |
| 49 | — | MarylandMD | 48 | 9 | -29% | 63% | 47.4% | 0.12 |
| 50 | — | New YorkNY | 30 | 20 | -20% | 86% | 100% | 0.23 |
Want the full data center buildout report?
Get the complete state-by-state breakdown, delivered to your inbox.
▾Methodology
- Pipeline index (data centers filed, in construction, or operating) — each state's pipeline of distinct data center projects in Spark's infrastructure database that have reached at least one of these stages on or before 2026-10-15: a permit filed, construction started, or fully operational. It counts individually tracked projects rather than individual buildings, so a single large campus can span many buildings under one or a handful of tracked projects. We publish this measure as an index (the largest state = 100) and as a share of the national pipeline, because relative position is what the ranking turns on.
- Permits filed (Q3 2025 / Q3 2026) — permit-filed milestones logged for data center projects in the same three-month window (July 1 – September 30) of each year, so the two years compare like for like. We publish the change between the two years rather than raw filing counts.
- Growth rate — the change in permit filings between Q3 2025 and Q3 2026, calculated as (2026 filings − 2025 filings) ÷ (2026 filings + 2025 filings). This symmetric formula is bounded to ±100%, so a state going from a near-zero base doesn't produce a runaway percentage.
- Approval rate (Q3 2026) — of the permit decisions (approved or denied) recorded for data center projects between July 1 and September 30, 2026 - the same window used for the growth-rate column - the share that were approved. Permits still pending a decision are excluded. States with a “—” had no decided permits in this window.
- Active moratoria — the share of a state's counties with a currently active, adopted data-center moratorium, out of all counties in the state (townships and other sub-county jurisdictions aren't counted). If a state has adopted a genuine statewide moratorium, this shows 100% regardless of county count. Determined from a text-based classification of authority decisions, so treat it as directional rather than a legal determination.
- Active opposition (events per project) — the number of public-opposition events (contested hearings, organized resident pushback, or social posts flagged as opposition) logged against data center projects in a state during the same Q3 2026 window used above, scaled to a six-month equivalent in the score so it stays on the same calibration as earlier editions, divided by the size of that state's data center pipeline. Dividing by the pipeline keeps a state with a large pipeline from being penalized just for having more surface area for opposition to occur.
- Spark Data Center Score — Spark's proprietary 0–100 composite, weighing five inputs: relative data center pipeline size, permit-filing growth rate, approval rate, active-moratoria share, and opposition events per project (a higher share of active moratoria or a higher opposition level each pull the score down). Each input is normalized against a fixed reference range, calibrated once rather than rescaled on every refresh, so a state's score only moves when its own numbers move — not because another state's range shifted. Total data centers are measured as each state's share of the national pipeline against a fixed reference, so the score depends on relative position rather than absolute counts (the same applies to the volume dampening described below, which uses each state's share of national filing and decision volume); growth rate -100% to +100%; approval rate 0% to 100%; moratoria share 0% to 100%; opposition 0 to 2.0 events per project. Growth rate, approval rate, and opposition are also dampened toward a fixed historical baseline in proportion to how much volume backs them, so a handful of events in a small state doesn't swing the score as much as the same events would in an established market — states with no decided permits in the window are anchored to an 80% baseline approval rate rather than penalized for having no data yet. Rank reflects this score, highest to lowest. The exact weighting of each input is proprietary.
- vs H1 — how a state's rank has moved since the H1 2026 ranking published August 18, 2026.
- Data is sourced from Spark's proprietary infrastructure tracking database, covering permitting authority decisions, hearings, and construction/operational milestones nationwide. Figures reflect what has been captured and verified as of the data cutoff and will shift as new filings and decisions are recorded.
Go deeper
More from Spark on data center permitting, zoning, and development.
US data center map
An interactive map of data center sites tracked nationwide.
State permitting guides
Jurisdiction-level zoning and permitting detail for every state in this ranking.
Customer case studies
How developers use Spark to cut site diligence and permitting time.
Podcasts
Spark's team on AI, permitting bottlenecks, and infrastructure development.
SparkNotes blog
Industry insights and updates on energy and data center infrastructure.
Planning a data center in one of these states?
Get a permit matrix with a jurisdiction-level breakdown of zoning, permitting, and approval timelines for your specific site.
Explore permit matrices